Installation
STEP1:
One of our friendly dealers will come to site to evaluate positioning, access and pool
requirements.
STEP2:
A Template of the pool shape is laid out on the ground to create the initial shape of the pool.
STEP3:
The measurements of the pool are checked and squared up relevant to houses or other
surrounding structures. Once we are happy with the pool positioning an excavator is ready to
start digging the pool hole.
STEP4:
The pool hole is then dug and the excavated materials are removed from site.
STEP5:
The base material is then screaded to set heights for the pool to be placed into position.
STEP6:
The crane is then positioned and set up.
STEP7:
The pool is then connected to the crane and the lift begins.
STEP8:
The pool is then lowered down into position.
STEP9:
The pools final sitting position is measured and squared up before the crane leaves the site,
levels at this stage are also checked.
STEP10:
Pipework, filters and lights are all connected and the process of back filling the water begins.
STEP11:
The concrete bond beam/slab are then prepared and poured awaiting pavers/tiles to finish off
the pool.
STEP12:
The coping pavers/tiles and fencing are installed and your swimming pool water is balanced
ready for swimming.